Good Morning Community Members,
MedStar Georgetown to Install Third and Final Tower Crane Dec. 11-14
MedStar Georgetown is planning to install the third and final tower crane on the Medical/Surgical Pavilion construction site on Dec. 11-14. As was the case for the first two tower cranes installed earlier this year, work to build the third tower crane will be done over the course of four consecutive days from 7 a.m. to 7 p.m. each day. Following is the schedule of activity, as planned and agreed upon with the community:
Friday, Dec. 11: Bring mobile crane to site and set up (3 oversized load deliveries)
Saturday, Dec. 12: Bring 13 loads (not oversized) of 20’ tower crane sections and erect with mobile crane
Sunday, Dec. 13: Bring an additional 13 loads (not oversized) of 20’ tower crane sections and complete assembly of the tower crane
Monday, Dec. 14: Dismantle mobile crane and leave site (3 oversized loads)
For safety reasons, these activities must occur during the day due to the number of deliveries and critical rigging that must be done to erect the tower crane. All oversized deliveries to the construction site will follow routes prescribed by DDOT as part of the permitting process, and will not impede traffic flow on Reservoir Road.
If you have any questions about these Medical/Surgical Pavilion construction activities, please contact Construction Executive Matt Maio, Trammell Crow Company, at medstarhospitaltrammellcrow@gmail.com or 202-360-5735.
Best Regards,
Regina Knox Woods
______________________________
Regina Knox Woods, Vice President
Government Affairs for the District of Columbia
MedStar Health
110 Irving Street, NW
East Building 8111
Washington, D.C. 20010
P: 202-877-0382
C: 202-288-0893
Assistant: Ruby Price
P: 410-772-6687
P: 202-877-8296 MWHC
C: 301-742-0637
MedStar Health—It’s how we treat people.